If the Contract has Milestone dates specified in it then it is binding to the Contractor to achieve and include in his submitted program of works.
If the Contract is silent, then the only restriction is the end delivery date.
If the Client has sufficient reason to reject any part in the submitted program of works "Material submittals" or others, then it is the Contractors responsbility to submit the necessary resources in written supporting his reasons for submitting the proposed program of works.
Unless you have specific clause in your Contract stating that you must respects the dates the Client gives you for any part of the project, then your responsibility is to complete the job on time. The Program that you submit must show that, by showing all the necessary activities, milestones, resources, and durations to complete the project.
A copy of the FIDIC hard or soft can be purchased from FIDIC at www.fidic.org for small fees.
Thank you for deatailed reply and for your great information but do the client have the right to apply his whole program and not accept any date for example for material submission not matching with his program furthermoe,you have soft copy for fidic specially about claims if you have could you provide me
Per FIDIC 1999 clause 8.3, the Contractor shall submit a detail time program to the Engineer within 28 days from receiving commencement order.
The Engineer reviews the submitted program and either approve it or send it back with comments for resubmittal.
On larger projects, the Client might have a Construction Manager who is managing many Contractors. In this event, a separate Planning entity would be available at site to manage the entire works.
The Contract requirements pertaining to the scope, milestones, and others must be listed in the program.
If you have more specific questions, please let us know.
Samer
Member for
20 years 3 months
Member for20 years4 months
Submitted by Charleston-Jos… on Thu, 2009-01-08 08:33
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2. The
Cheers
Happy Planning and Scheduling
Member for
20 years 3 months
Member for20 years4 months
Submitted by Charleston-Jos… on Thu, 2009-01-08 08:33
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2.
Cheers
Happy Planning and Scheduling
Member for
20 years 3 months
Member for20 years4 months
Submitted by Charleston-Jos… on Thu, 2009-01-08 08:32
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2.
Cheers
Happy Planning and Scheduling
Member for
20 years 3 months
Member for20 years4 months
Submitted by Charleston-Jos… on Thu, 2009-01-08 08:32
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2.
Member for
17 years 3 monthsRE: important question in fidic?
Dear Amro,
If the Contract has Milestone dates specified in it then it is binding to the Contractor to achieve and include in his submitted program of works.
If the Contract is silent, then the only restriction is the end delivery date.
If the Client has sufficient reason to reject any part in the submitted program of works "Material submittals" or others, then it is the Contractors responsbility to submit the necessary resources in written supporting his reasons for submitting the proposed program of works.
Unless you have specific clause in your Contract stating that you must respects the dates the Client gives you for any part of the project, then your responsibility is to complete the job on time. The Program that you submit must show that, by showing all the necessary activities, milestones, resources, and durations to complete the project.
A copy of the FIDIC hard or soft can be purchased from FIDIC at www.fidic.org for small fees.
Good luck,
Samer
Member for
16 years 10 monthsRE: important question in fidic?
Dear Samer,
Thank you for deatailed reply and for your great information but do the client have the right to apply his whole program and not accept any date for example for material submission not matching with his program furthermoe,you have soft copy for fidic specially about claims if you have could you provide me
Thank you very much
Amro
eng_amrelsaied@hotmail.com
Member for
17 years 3 monthsRE: important question in fidic?
Dear Amro,
Per FIDIC 1999 clause 8.3, the Contractor shall submit a detail time program to the Engineer within 28 days from receiving commencement order.
The Engineer reviews the submitted program and either approve it or send it back with comments for resubmittal.
On larger projects, the Client might have a Construction Manager who is managing many Contractors. In this event, a separate Planning entity would be available at site to manage the entire works.
The Contract requirements pertaining to the scope, milestones, and others must be listed in the program.
If you have more specific questions, please let us know.
Samer
Member for
20 years 3 monthsRE: important question in fidic?
Amro,
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2. The
Cheers
Happy Planning and Scheduling
Member for
20 years 3 monthsRE: important question in fidic?
Amro,
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2.
Cheers
Happy Planning and Scheduling
Member for
20 years 3 monthsRE: important question in fidic?
Amro,
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2.
Cheers
Happy Planning and Scheduling
Member for
20 years 3 monthsRE: important question in fidic?
Amro,
The FIDIC is not specific on this actions by the client.
But there are supplemental agreement, condition of particular applications, specification regarding planning, milestone embedded in the contract etc., etc. that may form as part of the contract document. As such, then depending on the attachment to the whole contract document, the client may have the right or may have already put the programe and will do the monitoring.
Basically, the client will only provide milestone dates, basic activities at level 1 or 2.