Rain Days - EOT Claim.

Member for

19 years 2 months

if the rainfall was the biggest in 50years so you are entiteled to claim EOT and you can create a separete additioal event call(Delay due to un expected heavy rain)with total duration of the stoping period and link this activity with the effectet perdessors and sucessors and run the program to see the impact of this delay event on the approved work program.

Member for

19 years 4 months

In My scenario the rainfall was the biggest in 50years so we got a reprieve.

Member for

18 years 3 months

You are right ravi...



there should be a physical obstruction to claim for an EOT. Just a heavy rainfall (without any obstruction) will not help in this case.



regards,

pradeep

Member for

18 years 5 months

Marcio / Sarthy,



It all depends weather there is a specific clause in the contract or not for rainy days



If u r referring Clause 12.2 of 1987 FIDIC, it states the events which you cannot forsee.



In countries like Brazil, where Marcio is working or in India, where Sarthy has done has done this project, you just CANNOT say that you have not forseen the rain.



You can ask EOT for either HEAVY RAINFALL (Not seen in last 10 years or so) or for FLOOD (which pradeep has mentioned)



I am doubtful, weather you can claim EOT for rainy days.



Am I right?


Member for

19 years 4 months

In a previous project of mine we had done something similar and have been successful it getting it. We started out by submitting the rainfall data for the previous day in our Daily Progress Report and then asked for an additional 60 days because of Rain and Other COnsequential Delays in line with the Physical Obstruction to the SIte criteria. To Support this we also furnished documents from the Local Meterological Office...and other similar data.



We Were Able to Wrest 27days from the Employer / Consultant.

It was For a FLyover Project.



Regards,



Vijay

Member for

19 years 3 months

Rite Pradeep....



this is a systematic approach and a goood procedure...



even the same procedure, we used in 2 of my previous projects and dealt with Time extension...



J

Member for

18 years 3 months

Dear Marcio,



This is what i can suggest...

Refer clause 12.2 of FIDIC 1987 where the contractor can claim for EOT when he could not forsee an event. This i can say if the work site was flooded (which is a physical obstruction) and could not carry out the work.



Be sure to support your claim by getting the history of weather data for the last few years (say 10-15 years) from the meteorological (hope i spell right ) department. If there was heavy rain which no one could have predicted (in this case experienced contractor) then i am sure you can get EOT. However, it depends on the relation your company has with engineer and employer.



Actually we had got EOT in one of our projects way back; atleast half the claim of EOT without any cost / claim on prelims. We agreed and the chapter was closed. This does not allow you to make any reference ;)



regards,

pradeep

Member for

20 years

Thank u all...



There is a contract clause about that. We are studying tha case.



Regards.

Member for

19 years 3 months

Hi Normally u will not get it? read carefully the contract. if they mention and rainy day and windy day etc etc to be the part of contract duration u cant claim separate but u can put a justifiable duration on account of high wind /rain, by refering prvious data!!

Member for

22 years 4 months

Seek clause related to rains or unprecedented rains in your Contract Agreement. Based on which you can claim and get EOT for this item.