Have you plugged the ’delays’ into the as planned / baseline programme. If so, this does not demonstrate actual delay. You will have to demonstrate that you were ready to pour the concrete on a certain date, say 1 March, and the concrete was not delivered until 4 March, and therefore 3 days delay. AND that this work activity was on the actual critical path at the time.
Roger Gibson
I have a question here, first - what is the name of this method of calculating- Inserting delay in The Baseline "As-Planned" Schedule.
Is that a recomended Approach or not?
What would be poosible differences b/w As-Built/TIA and this method( inserting delay in the baseline only).
Please elobrate - if possoble with example.
Regards
Rana
Member for
20 years 8 months
Member for20 years8 months
Submitted by Francis Moyala… on Mon, 2007-07-09 04:16
I plugged the actual pour dates as the early finish constraint in the program,
And this delay is in the critical path, if you have got a concrete on 1st march that is actually the early start date, when the planned date was 1st of Jan , i.e you are already delayed by 2 months with several other delays as i already mentioned.....
So how can I show in the final completion date as 3 days delay ???????????
Member for
24 years 5 months
Member for24 years5 months
Submitted by Roger Gibson on Mon, 2007-07-09 03:43
Have you plugged the delays into the as planned / baseline programme. If so, this does not demonstrate actual delay. You will have to demonstrate that you were ready to pour the concrete on a certain date, say 1 March, and the concrete was not delivered until 4 March, and therefore 3 days delay. AND that this work activity was on the actual critical path at the time.
Roger Gibson
Member for
20 years 8 months
Member for20 years8 months
Submitted by Francis Moyala… on Mon, 2007-07-09 03:42
Situation-i have made a cause & impact program for claiming extension of time plugging in 44 delay causes from the client side. Of this 22 causes are due to concrete delivery delays which is client supplied.
Issue-concrete delivery has delayed for maximum for 1 to 2 days in individual cases.....that means total impact must be 1 or 2 days on the finish date, from case to case.
- I made the eot program plugging in all delays, with the concrete actual delivery date as the constraint. in this case, individual delivery delay of 1 or 2 days shows a total impact on the finish date of 10 to 20 days, since the project was already in a delay...
- in this case, how can i convince the client/engineer, since my critical/driving delaying event is the concrete delivery(latest)for the last slab poured- it is obvious coz that date is the latest one, taking in to account of all existing delays...
can anyone suggest a suitable format to present this case, so that we can grab the eot ...
Thanks in advance for all your valuable inputs,
cheers,
Francis Varghese
Member for
21 years 5 months
Member for21 years5 months
Submitted by Chris Oggham on Mon, 2007-07-09 03:37
Member for
19 years 10 monthsHi Rana Welcome to Planning
Hi Rana
Welcome to Planning Planet
You have just replied to a topic that is 5 years old.
It is most unlikely that you will get any response from the original contributors.
Please restrict your comments to current discussions or start a new topic.
Best regards
Mike Testro
Member for
15 years 10 monthsDear Roger GibsonFrom the
Dear Roger Gibson
From the above reply to Francis
Francis,
Have you plugged the ’delays’ into the as planned / baseline programme. If so, this does not demonstrate actual delay. You will have to demonstrate that you were ready to pour the concrete on a certain date, say 1 March, and the concrete was not delivered until 4 March, and therefore 3 days delay. AND that this work activity was on the actual critical path at the time.
Roger Gibson
I have a question here, first - what is the name of this method of calculating- Inserting delay in The Baseline "As-Planned" Schedule.
Is that a recomended Approach or not?
What would be poosible differences b/w As-Built/TIA and this method( inserting delay in the baseline only).
Please elobrate - if possoble with example.
Regards
Rana
Member for
20 years 8 monthsRE: TIME EXTENSION CLAIM FOR MULTIPLE DELAYS
Roger,
I plugged the actual pour dates as the early finish constraint in the program,
And this delay is in the critical path, if you have got a concrete on 1st march that is actually the early start date, when the planned date was 1st of Jan , i.e you are already delayed by 2 months with several other delays as i already mentioned.....
So how can I show in the final completion date as 3 days delay ???????????
Member for
24 years 5 monthsRE: TIME EXTENSION CLAIM FOR MULTIPLE DELAYS
Francis,
Have you plugged the delays into the as planned / baseline programme. If so, this does not demonstrate actual delay. You will have to demonstrate that you were ready to pour the concrete on a certain date, say 1 March, and the concrete was not delivered until 4 March, and therefore 3 days delay. AND that this work activity was on the actual critical path at the time.
Roger Gibson
Member for
20 years 8 monthsRE: TIME EXTENSION CLAIM FOR MULTIPLE DELAYS
Is it Ok Chris????????
Member for
20 years 8 monthsRE: TIME EXTENSION CLAIM FOR MULTIPLE DELAYS
Situation-i have made a cause & impact program for claiming extension of time plugging in 44 delay causes from the client side. Of this 22 causes are due to concrete delivery delays which is client supplied.
Issue-concrete delivery has delayed for maximum for 1 to 2 days in individual cases.....that means total impact must be 1 or 2 days on the finish date, from case to case.
- I made the eot program plugging in all delays, with the concrete actual delivery date as the constraint. in this case, individual delivery delay of 1 or 2 days shows a total impact on the finish date of 10 to 20 days, since the project was already in a delay...
- in this case, how can i convince the client/engineer, since my critical/driving delaying event is the concrete delivery(latest)for the last slab poured- it is obvious coz that date is the latest one, taking in to account of all existing delays...
can anyone suggest a suitable format to present this case, so that we can grab the eot ...
Thanks in advance for all your valuable inputs,
cheers,
Francis Varghese
Member for
21 years 5 monthsRE: TIME EXTENSION CLAIM FOR MULTIPLE DELAYS
FRANCIS,
Why are you shouting?
It makes things difficult to read when you have everything in upper case text?
Chris