Liquidated Damages

Member for

19 years 2 months

In UAE ,we are using the general condition of contract which almost has ben extracted from FIDIC.



we have never used JCT.

Member for

19 years 11 months

Thax Andrew for ur valued comments.



sam

Member for

20 years 10 months

It does depend on what version of the JCT contract you are working on though - I’m assuming it’s 1980 or later.

Member for

20 years 10 months

Samagata,



Both the issue of a certificate and a request made in writing by the employer to deduct liquidated damages, are condition precedents to the Employer deducting liquidated damages.



A certificate of non completion can not be issued after issue of the final certificate and so if not issued before the final certificate, the employer will lose his rights to liquidated damages.

Member for

19 years 2 months

The client can not lost his right due to non issuance of ’no effective non-completion certificate’ .

As per the contract the only certificate which can prove that the contractor has completed the woke and maintane it properly is the maintanace certificate.



That mean even the issuance of taking over certificate can not hold the client right to deduct the liquidqted dameges at any time befre issuing maintanace certificate.

Non issuance of ’ non-completion certificate’can not consider as basis for any contractual issues .

Member for

21 years 9 months

Sam,



Can a non-completion certificate be backdated?



Regards,

Larry

Member for

19 years 11 months

hi akhilesh,



JCT stands for Joint Contracts Tribunal. its a Standard form of Construction Contract like FIDIC.



sam

Member for

20 years 3 months

Hi Sam



[English only, please - The Moderator]

Wht’s JCT contract?





Regards



Akhilesh Shukla