percent complete in p3.1

Member for

20 years 5 months

Hi,

Maybe u can create a dummy column, goto "data> custom data item" then create a column, use Global Change to make the calaculation and click run transfer the result to the dummy column you already create.

Member for

20 years 3 months

Hi Ayman,



I think it is not possible.



The percent progress alway round off to the whole number without decimal.



Lets hear from other PP, maybe im wrong. And I also want to be corrected if my reply is wrong in this thread.



Cheers,



Charlie