There are two options when using Powerproject in an Enterprice Environment:
Either you may have all your projects in one database in a similar way to P6, with similar advantages and disadvantages of having all the projects in one database as with P6, or
You can load your projects into a web app called Project Vision which is also a very powerfull tool where your projects are downloaded from the web to be worked on on a PC, like checking out, and then they are uploaded again when the user has completed the update. I would think Project Vision would resolve remote site latency issues, but my experiance is mainly with multiple projects in a database.
Elecosoft Powerproject is designed for the Building and Construction industries, unike P6 and MSP that were both developed for IT and Business Development projects and it has a lot of the functions I am seeking from construction software including built in BIM functions.
Member for
24 years 6 monthsThere are two options when
There are two options when using Powerproject in an Enterprice Environment:
Elecosoft Powerproject is designed for the Building and Construction industries, unike P6 and MSP that were both developed for IT and Business Development projects and it has a lot of the functions I am seeking from construction software including built in BIM functions.
You may wish to read my article on the Comparison of P6, MSP and Powerproject
I also publish training material for Elecosoft Powerproject, click on this link for details.
Regards
Paul E Harris