Asta Powerproject Member for 19 years 8 months Member for 19 years 8 months Submitted by Konstantinos P… on Fri, 2022-01-28 16:23 Permalink Hello Martin!I think that Hello Martin! I think that PowerProject does that as it treats each progressed (actualised) part of the task as a separate task. You can use the Unique Task ID field instead and that doesn't change. Kind regards, Konstantinos Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2022-01-11 13:41 Permalink Hi MartinI have not yet Hi Martin I have not yet downloaded v 16 but it would be that the software is keeping a rolling record of your previous entries. By recalling the posting date of your earlier progress you can download the progress. This is essntial when setting up an As Built programme for an EOT claim. Best regards Mike T. Log in or register to post comments
Member for 19 years 8 months Member for 19 years 8 months Submitted by Konstantinos P… on Fri, 2022-01-28 16:23 Permalink Hello Martin!I think that Hello Martin! I think that PowerProject does that as it treats each progressed (actualised) part of the task as a separate task. You can use the Unique Task ID field instead and that doesn't change. Kind regards, Konstantinos
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2022-01-11 13:41 Permalink Hi MartinI have not yet Hi Martin I have not yet downloaded v 16 but it would be that the software is keeping a rolling record of your previous entries. By recalling the posting date of your earlier progress you can download the progress. This is essntial when setting up an As Built programme for an EOT claim. Best regards Mike T.
Member for
19 years 8 monthsHello Martin!I think that
Hello Martin!
I think that PowerProject does that as it treats each progressed (actualised) part of the task as a separate task.
You can use the Unique Task ID field instead and that doesn't change.
Kind regards,
Konstantinos
Member for
19 years 10 monthsHi MartinI have not yet
Hi Martin
I have not yet downloaded v 16 but it would be that the software is keeping a rolling record of your previous entries.
By recalling the posting date of your earlier progress you can download the progress.
This is essntial when setting up an As Built programme for an EOT claim.
Best regards Mike T.