Early & Late "banana curve"

Member for

21 years 8 months

Member for

17 years 4 months

Hi Chris

 

You could use the EA Reporter under the Project Tab. Make sure you select the duration as the quantity to report on. You will need to baseline the project first.

When you get to the baselines section report against the baseline you just did - ASAP baseline (top selection), and make sure that "use float end dates from my ASAP baseline is selcted (bottom selection). Choose current view & run.

 

The results will depend on how well your netwrok is linked.

 

Good luck

 

Regards

 

Andrew