Asta Powerproject Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2020-11-13 11:29 Permalink Hi Steve,In the View tab, Hi Steve, In the View tab, open Filter and click New Edit the Criteria #1 row, Select Specific activity types: tasks, milestones, then Next Select Float (Slack?) and Criticity, then Next Click Show activities with specified float (radio button # 4), Total float, Less than, and enter a value in the Duration field As I am working with PowerProject in French, I hope you will understand my explanations Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Fri, 2020-11-13 11:29 Permalink Hi Steve,In the View tab, Hi Steve, In the View tab, open Filter and click New Edit the Criteria #1 row, Select Specific activity types: tasks, milestones, then Next Select Float (Slack?) and Criticity, then Next Click Show activities with specified float (radio button # 4), Total float, Less than, and enter a value in the Duration field As I am working with PowerProject in French, I hope you will understand my explanations Alexandre
Member for
22 years 9 monthsHi Steve,In the View tab,
Hi Steve,
In the View tab, open Filter and click New
Edit the Criteria #1 row,
Select Specific activity types: tasks, milestones, then Next
Select Float (Slack?) and Criticity, then Next
Click Show activities with specified float (radio button # 4), Total float, Less than, and enter a value in the Duration field
As I am working with PowerProject in French, I hope you will understand my explanations
Alexandre