Asta Powerproject Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2020-03-23 16:58 Permalink Hello BenThank you!Shame on Hello Ben Thank you! Shame on me, I should have found it by myself! Alexandre Member for 13 years 9 months Member for 13 years 9 months Submitted by Ben Taunt on Fri, 2020-03-20 17:49 Permalink Hi Alexandre,On the View Hi Alexandre, On the View ribbon, you can change the default snapping unit in the drop down list: [[wysiwyg_imageupload:7328:]] I just tested it and it is this field that controls what happens when you just tap "5" into the duration field on the spreadsheet. Thanks, Ben @ Powerproject Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2020-03-23 16:58 Permalink Hello BenThank you!Shame on Hello Ben Thank you! Shame on me, I should have found it by myself! Alexandre
Member for 13 years 9 months Member for 13 years 9 months Submitted by Ben Taunt on Fri, 2020-03-20 17:49 Permalink Hi Alexandre,On the View Hi Alexandre, On the View ribbon, you can change the default snapping unit in the drop down list: [[wysiwyg_imageupload:7328:]] I just tested it and it is this field that controls what happens when you just tap "5" into the duration field on the spreadsheet. Thanks, Ben @ Powerproject
Member for
22 years 9 monthsHello BenThank you!Shame on
Hello Ben
Thank you!
Shame on me, I should have found it by myself!
Alexandre
Member for
13 years 9 monthsHi Alexandre,On the View
Hi Alexandre,
On the View ribbon, you can change the default snapping unit in the drop down list:
[[wysiwyg_imageupload:7328:]]
I just tested it and it is this field that controls what happens when you just tap "5" into the duration field on the spreadsheet.
Thanks,
Ben @ Powerproject