Alexandre, 

 

Thanks for your help, I managed to correct it. 

Dominic 

Member for

22 years 9 months

Hello Dominic,

I suspect that the Project Completion milestone has a hard constraint date as Start On, Finish On later than the scheduled finish date of the last-in-sequence activity of the project.

Have a try by removing this constraint date and give your milestone the project last activity as a predecessor

Alexandre