I suspect that the Project Completion milestone has a hard constraint date as Start On, Finish On later than the scheduled finish date of the last-in-sequence activity of the project.
Have a try by removing this constraint date and give your milestone the project last activity as a predecessor
Member for
8 years 5 monthsAlexandre, Thanks for your
Alexandre,
Thanks for your help, I managed to correct it.
Dominic
Member for
22 years 9 monthsHello Dominic,I suspect that
Hello Dominic,
I suspect that the Project Completion milestone has a hard constraint date as Start On, Finish On later than the scheduled finish date of the last-in-sequence activity of the project.
Have a try by removing this constraint date and give your milestone the project last activity as a predecessor
Alexandre