Certainly not a licensing issue - there is nothing we can do within the tool to restrict you planning out as far as you wish into the future!
Instead, it sounds to me as though your calendar or working pattern are set such that post 2020 is marked as "non-working time". If you right click on your default calendar in the list on the left-hand side, please check the Finsh Date for your Working Pattern Assignment. You might need to punt this out a few more years to open up the dates you need to see.
Member for
13 years 9 monthsHi Keiron,Certainly not a
Hi Keiron,
Certainly not a licensing issue - there is nothing we can do within the tool to restrict you planning out as far as you wish into the future!
Instead, it sounds to me as though your calendar or working pattern are set such that post 2020 is marked as "non-working time". If you right click on your default calendar in the list on the left-hand side, please check the Finsh Date for your Working Pattern Assignment. You might need to punt this out a few more years to open up the dates you need to see.
Let me know if that solves things.
Thanks,
Ben @ Powerproject