Asta Powerproject Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2019-04-15 16:31 Permalink Hi TomWelcome to planning Hi Tom Welcome to planning plannet. You are showing a different calendar on the summery bar - you can only have one. When you add a different calendar the sytem asks if you want to switch the display - you declined. The tasks underneath will have the correct shading. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2019-04-15 16:31 Permalink Hi TomWelcome to planning Hi Tom Welcome to planning plannet. You are showing a different calendar on the summery bar - you can only have one. When you add a different calendar the sytem asks if you want to switch the display - you declined. The tasks underneath will have the correct shading. Best regards Mike Testro
Member for
19 years 10 monthsHi TomWelcome to planning
Hi Tom
Welcome to planning plannet.
You are showing a different calendar on the summery bar - you can only have one.
When you add a different calendar the sytem asks if you want to switch the display - you declined.
The tasks underneath will have the correct shading.