I have exported data using the histonochart template this however gives me the rsource or cost item in the columns and the date/ alocation in rows. Does anyone know how to transpose this data before it is in excel so that the dates are the columns and resource/ cost allocaton are the rows?
Member for
9 yearsI have exported data using
I have exported data using the histonochart template this however gives me the rsource or cost item in the columns and the date/ alocation in rows. Does anyone know how to transpose this data before it is in excel so that the dates are the columns and resource/ cost allocaton are the rows?
Regards
Chris
Member for
19 years 10 monthsHi Austin Welcome to Planning
Hi Austin Welcome to Planning Planet
If you right click the histogram and at the bottom there is Export to Excell.
You then have a choice of templates.
If you just want the data then select histnochart.xlt.
Other templates will generate the data and the chart.
Best regards
Mike Testro