Hi Chris
In the library there is a feature to allocate names to different types of links.
You can highlight FS links or Lag links and give them a name.
I would use a leading numeral so they are easy to find in the drop down list - 01 FS - 02 Lag etc.
You can then either filter on the name or use a column to show the names.
Just copy paste the column names on a spreadsheet and you can count them from there.
Best regards
Mike T.
Hi Chris
Thanks for putting me in touch with this DCMA 14 concept. I have been banging on about these topics for years.
See my PP post on "Ban these planning abominations".
It seems the DCMA may be an offshoot of the US Corps of Engineers who gave us the "Windows System" back in the 50's
Every one of the 14 points can be checked individually by the relevant ASTA filters but there is no "one shot" button.
Asta does not allow negative float anyway so that sequence is not valid.
Best regards
Mike Testro
Member for
24 years 4 monthsI believe accumen can do the
I believe accumen can do the analysis on an asta plan.
Member for
19 years 10 monthsHi Chris In the library there
Hi Chris
In the library there is a feature to allocate names to different types of links.
You can highlight FS links or Lag links and give them a name.
I would use a leading numeral so they are easy to find in the drop down list - 01 FS - 02 Lag etc.
You can then either filter on the name or use a column to show the names.
Just copy paste the column names on a spreadsheet and you can count them from there.
Best regards
Mike T.
Member for
9 yearsMike,Thanks for the reply,I
Mike,Thanks for the reply,
I take it you would apply filters and then just count the number of activities in each filter and use uin the relevant formulas then?
How would you create for the number of activities with finish to start relationships or Lags?
I think I can create relevant filters for the checks that are based on progress but not the ones based on logic as above.
Any help would be appreciated.
Thanks
Chris
Member for
19 years 10 monthsHi Chris Thanks for putting
Hi Chris
Thanks for putting me in touch with this DCMA 14 concept. I have been banging on about these topics for years.
See my PP post on "Ban these planning abominations".
It seems the DCMA may be an offshoot of the US Corps of Engineers who gave us the "Windows System" back in the 50's
Every one of the 14 points can be checked individually by the relevant ASTA filters but there is no "one shot" button.
Asta does not allow negative float anyway so that sequence is not valid.
Best regards
Mike Testro