Asta Powerproject Member for 10 years 2 months Member for 10 years 2 months Submitted by Yasine on Mon, 2018-01-22 12:34 Permalink You could baseline your as You could baseline your as planned programme and then insert this in your as built programme. Then format the chart to show the baseline on its own line which will show you the difference in durations. Log in or register to post comments
Member for 10 years 2 months Member for 10 years 2 months Submitted by Yasine on Mon, 2018-01-22 12:34 Permalink You could baseline your as You could baseline your as planned programme and then insert this in your as built programme. Then format the chart to show the baseline on its own line which will show you the difference in durations.
Member for
10 years 2 monthsYou could baseline your as
You could baseline your as planned programme and then insert this in your as built programme.
Then format the chart to show the baseline on its own line which will show you the difference in durations.