The hammock bar will have its own set of data in the columns.
You can create a hammock effect between baselines and live dates by using milestones aligned to the baseline and fixed with a flag and and another linked to the live data and then summarised.
Member for
19 years 10 monthsHi ChrisThe hammock bar will
Hi Chris
The hammock bar will have its own set of data in the columns.
You can create a hammock effect between baselines and live dates by using milestones aligned to the baseline and fixed with a flag and and another linked to the live data and then summarised.
Best regards
Mike T.
Member for
9 yearsThanks Mike,I take it I add
Thanks Mike,
I take it I add the hammock bar to the live data, this will give me a visual but looking to quantify in a columnn aswell.
Member for
19 years 10 monthsHi ChrisDisplay the baselines
Hi Chris
Display the baselines on their own lines and you can see the dates for each one.
You can then disply the delay periods for each section using hammock bars.
Best regards
Mike T.