Asta Powerproject Member for 24 years 4 months Member for 24 years 5 months Submitted by Andrew Pearce on Mon, 2018-04-09 17:17 Permalink Hi Daniel,Are you reviewing a Hi Daniel, Are you reviewing a PDF or soft copy of the schedule? I suspect that the file has not been rescheduled to the progress update date. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2017-10-21 12:26 Permalink Hi DanielI do not recognise Hi Daniel I do not recognise that situation in any aspect of asta Powerproject. The software does not schedule negative float but flags up a warning that it has been created and will not continue until the blockage has been removed. Best regards Mike T Log in or register to post comments
Member for 24 years 4 months Member for 24 years 5 months Submitted by Andrew Pearce on Mon, 2018-04-09 17:17 Permalink Hi Daniel,Are you reviewing a Hi Daniel, Are you reviewing a PDF or soft copy of the schedule? I suspect that the file has not been rescheduled to the progress update date.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2017-10-21 12:26 Permalink Hi DanielI do not recognise Hi Daniel I do not recognise that situation in any aspect of asta Powerproject. The software does not schedule negative float but flags up a warning that it has been created and will not continue until the blockage has been removed. Best regards Mike T
Member for
24 years 4 monthsHi Daniel,Are you reviewing a
Hi Daniel,
Are you reviewing a PDF or soft copy of the schedule?
I suspect that the file has not been rescheduled to the progress update date.
Member for
19 years 10 monthsHi DanielI do not recognise
Hi Daniel
I do not recognise that situation in any aspect of asta Powerproject.
The software does not schedule negative float but flags up a warning that it has been created and will not continue until the blockage has been removed.
Best regards
Mike T