Asta Powerproject Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Mon, 2017-09-18 19:39 Permalink Mike, calendars and partial Mike, calendars and partial workloads can complicate the calculations. How would you model the cost of the crane for the following scenario? Crane sharing is very common. Member for 24 years 8 months Member for 24 years 9 months Submitted by Vladimir Liberzon on Sun, 2017-09-17 14:45 Permalink Mike,I do not understand your Mike, I do not understand your proposal. Please explain how these resource shall be assigned and how the project shall be leveled. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2017-09-17 13:21 Permalink Hi HarryThe only way I can Hi Harry The only way I can suggest is to set up 8 crane resource setcions each with 1 to 8 cost hours attached and allocate accordingly to the relevant task. You then have the problem of delivery and collection costs at each deployment unles it is on unpaid standby when not in use. Best regards Mike T. Member for 11 years Member for 11 years Submitted by h-angell on Fri, 2017-09-15 10:51 Permalink Hi Mike,It's a mobile crane Hi Mike, It's a mobile crane that would be called off as and when needed. Harry Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2017-09-14 15:48 Permalink Hi HarryIs it a mobile crane Hi Harry Is it a mobile crane that is called as and when or a fixed crane that is there all the time? Best regards Mike T. Log in or register to post comments
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Mon, 2017-09-18 19:39 Permalink Mike, calendars and partial Mike, calendars and partial workloads can complicate the calculations. How would you model the cost of the crane for the following scenario? Crane sharing is very common.
Member for 24 years 8 months Member for 24 years 9 months Submitted by Vladimir Liberzon on Sun, 2017-09-17 14:45 Permalink Mike,I do not understand your Mike, I do not understand your proposal. Please explain how these resource shall be assigned and how the project shall be leveled.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2017-09-17 13:21 Permalink Hi HarryThe only way I can Hi Harry The only way I can suggest is to set up 8 crane resource setcions each with 1 to 8 cost hours attached and allocate accordingly to the relevant task. You then have the problem of delivery and collection costs at each deployment unles it is on unpaid standby when not in use. Best regards Mike T.
Member for 11 years Member for 11 years Submitted by h-angell on Fri, 2017-09-15 10:51 Permalink Hi Mike,It's a mobile crane Hi Mike, It's a mobile crane that would be called off as and when needed. Harry
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2017-09-14 15:48 Permalink Hi HarryIs it a mobile crane Hi Harry Is it a mobile crane that is called as and when or a fixed crane that is there all the time? Best regards Mike T.
Member for
21 years 8 monthsMike, calendars and partial
Mike, calendars and partial workloads can complicate the calculations. How would you model the cost of the crane for the following scenario?
Crane sharing is very common.
Member for
24 years 8 monthsMike,I do not understand your
Mike,
I do not understand your proposal. Please explain how these resource shall be assigned and how the project shall be leveled.
Member for
19 years 10 monthsHi HarryThe only way I can
Hi Harry
The only way I can suggest is to set up 8 crane resource setcions each with 1 to 8 cost hours attached and allocate accordingly to the relevant task.
You then have the problem of delivery and collection costs at each deployment unles it is on unpaid standby when not in use.
Best regards
Mike T.
Member for
11 yearsHi Mike,It's a mobile crane
Hi Mike,
It's a mobile crane that would be called off as and when needed.
Harry
Member for
19 years 10 monthsHi HarryIs it a mobile crane
Hi Harry
Is it a mobile crane that is called as and when or a fixed crane that is there all the time?
Best regards
Mike T.