Import file

Member for

6 years 1 month

Hi Mike

Slight variation to this question, I receive files from Asta Power Project saved as an XER file which will import to the Standalone Desktop P6 (SQL lite), but fail when importing to the SQL Network databases.

 

Is there a specific method for Asta users to creat an XER file and have you encountered the issue before?

Member for

9 years

Thanks mike.

Member for

19 years 10 months

Hi Andy

Use File>Safe As>primavera .xer

Job done.

Best regards

Mike Testro