Asta Powerproject Member for 10 years 2 months Member for 10 years 2 months Submitted by Yasine on Wed, 2017-08-16 09:48 Permalink Mike,Thanks for the reply.I Mike, Thanks for the reply. I was just curious to see the colours that people normally use aside from the default. I am not sure what the "doberman's balls" concept is however. Regards Yasine Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2017-08-15 09:51 Permalink Hi YasineI use as standard Hi Yasine I use as standard for levels 1-4 as follows: Level 4 - Bright Green - Individual Tasks Level 3 - Bright Yellow - Section Summary Level 2 - Cyan - Zone Summary Level 1 - Dark Blue - Project This allows - Bright Red for delay events following the "doberman's balls" concept Baselines are black chequered At all costs avoid multiple displays of colours and patterns as the dazzle effect impacts on the visual presentation. I hope that helps. Best regards Mike Testro Log in or register to post comments
Member for 10 years 2 months Member for 10 years 2 months Submitted by Yasine on Wed, 2017-08-16 09:48 Permalink Mike,Thanks for the reply.I Mike, Thanks for the reply. I was just curious to see the colours that people normally use aside from the default. I am not sure what the "doberman's balls" concept is however. Regards Yasine
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Tue, 2017-08-15 09:51 Permalink Hi YasineI use as standard Hi Yasine I use as standard for levels 1-4 as follows: Level 4 - Bright Green - Individual Tasks Level 3 - Bright Yellow - Section Summary Level 2 - Cyan - Zone Summary Level 1 - Dark Blue - Project This allows - Bright Red for delay events following the "doberman's balls" concept Baselines are black chequered At all costs avoid multiple displays of colours and patterns as the dazzle effect impacts on the visual presentation. I hope that helps. Best regards Mike Testro
Member for
10 years 2 monthsMike,Thanks for the reply.I
Mike,
Thanks for the reply.
I was just curious to see the colours that people normally use aside from the default.
I am not sure what the "doberman's balls" concept is however.
Regards
Yasine
Member for
19 years 10 monthsHi YasineI use as standard
Hi Yasine
I use as standard for levels 1-4 as follows:
Level 4 - Bright Green - Individual Tasks
Level 3 - Bright Yellow - Section Summary
Level 2 - Cyan - Zone Summary
Level 1 - Dark Blue - Project
This allows - Bright Red for delay events following the "doberman's balls" concept
Baselines are black chequered
At all costs avoid multiple displays of colours and patterns as the dazzle effect impacts on the visual presentation.
I hope that helps.
Best regards
Mike Testro