Asta is a completely different system from P6 so it will take a little time to adjust but the effort will be well rewarded.
For one thing Asta will not accept negative float and the stated end date is advisory only.
In this way you cannot distort the logic - it is what it is.
You can change the finish date by moving the last milestone and flagging it to finish "On or After" then by setting the tasks ALAP they will move to the later date and turn critical.
You can also set the two dates - Earliest v Latest in the date columns.
Member for
19 years 10 monthsYes. But the point about
Yes. But the point about rules is knowing when it is safe to break them.
Member for
24 years 4 monthsMike dosnt that violate your
Mike dosnt that violate your planning rules on constraints and ALAP?
Member for
19 years 10 monthsHi HarryAsta is a completely
Hi Harry
Asta is a completely different system from P6 so it will take a little time to adjust but the effort will be well rewarded.
For one thing Asta will not accept negative float and the stated end date is advisory only.
In this way you cannot distort the logic - it is what it is.
You can change the finish date by moving the last milestone and flagging it to finish "On or After" then by setting the tasks ALAP they will move to the later date and turn critical.
You can also set the two dates - Earliest v Latest in the date columns.
Keep at it and use PP whenever you need us.
Best regards
Mike T.