Importing: PDF to ASTA?

Member for

19 years 10 months

Hi Steve

I have tried it - even by cropping the picture to show just the  columns - it doesn't work.

Now I just get someone to copy type into excell and then copy paste into PowerProject - it is still useless without the logic or the calendars.

When using this .pdf evidence in a delay analysis I use a Projected As Built method which tribunals like.

Best regards

Mike Testro

Member for

10 years

Just a thought you can put a pdf into excel / word  using a full pdf editor programme I haven't tried it with an asta pdf, at the worst it won't work at best you may get the programme task descriptions and task dates - may save a lot of typing??

 

Let me know if it works

 

Steve

Member for

8 years 10 months

Hi Mike, 

Thank you for your welcome. 

I asusmed as much, thank you for clarifying.

Best, C

Member for

19 years 10 months

Hi Camilla - Welcome to planning plannet

I am often faced with this problem and there is no way that a .pdf can be imported to a PowerProject file.

Particularly the logic is hidden together with all the other data such as float and calendars.

You may be able to export an image to word or excell via JPEG but youwill not get the true and full picture.

If such a document is the only evidence in a delay analysis I have to use a Projected as Built method.

Best regards

Mike Testro