Milestone

Member for

19 years 10 months

Hi Anu - Welcome to planning planet.

There are a number of ways to create a milesstone.

1. Type "0d" days in the duration field.

2. Right click the task and select Options > Change Into > Milestone

3. Hold the end of the task and drag sharp left to turn it into a milestone.

I hope that helps.

Best regards

Mike Testro