Asta Powerproject Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2016-10-05 11:08 Permalink Hi FarhadIn the column you Hi Farhad In the column you can format the duration by the Format Cells dropdown. You can do the same by selectiong the link and change the suffix ie 15w or 15d. As a general rule you should only use lead lags for curing or drying out periods and then it should be set as calendar days - 15ed. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2016-10-05 11:08 Permalink Hi FarhadIn the column you Hi Farhad In the column you can format the duration by the Format Cells dropdown. You can do the same by selectiong the link and change the suffix ie 15w or 15d. As a general rule you should only use lead lags for curing or drying out periods and then it should be set as calendar days - 15ed. Best regards Mike Testro
Member for
19 years 10 monthsHi FarhadIn the column you
Hi Farhad
In the column you can format the duration by the Format Cells dropdown.
You can do the same by selectiong the link and change the suffix ie 15w or 15d.
As a general rule you should only use lead lags for curing or drying out periods and then it should be set as calendar days - 15ed.
Best regards
Mike Testro