Formula Help - Omit summary tasks from formula?

Member for

18 years 5 months

This might work....
 
If(SubType=SummaryType, "", switch(
PlannedPercentComplete(CB,na)>PercentComplete,high,PlannedPercentComplete(CB,na)<=PercentComplete,low))

Member for

19 years 10 months

Hi Sam

The fact that the tick appears on summary bars is highly beneficial in that it allows you drill down through the summaries to find the problem task.

It is about time that Asta made the formula's more simple to administer by using a series of choices in drop down format.

Best regards

Mike Testro