Importing revised baseline w/ additional tasks into progress report.

Member for

9 years 4 months

Hi Sam,

The way i've done it is to import REV 2 baseline into REV 1 project, revert REV 1 to REV 2 baseline, this will bring any new tasks onto the programme. Then to get the REV 2 Basleine to appear under the correct tasks, i had to delete REV 2 baseline from REV 1 programme and import it again. 

Hope this helps.

Member for

9 years 2 months

Hi Charlotte, as above.  Accidently replied to myself!

Member for

9 years 2 months

Hi Charlotte, it is two seperate files Rev 1 & Rev 2.

 

The solution I came to was just to re-do each weeks progress against the Rev 2 with the new tasks.  Probably not the best way but it did the job.

Member for

9 years 4 months

Hi Sam,

I think i may have a solution for you, however there is just one thing i need to clarify, are you currently work between 2 project files? I.e REV 1.pp and REV 2.pp?

 

Regards,

Charlotte