Show Hammock allocation in a column at task level?

Member for

9 years 4 months

Hi Richard,

You can use the parent name colun which is found under the identification category.

Hope this helps :)

Member for

19 years 10 months

Hi Richard.

Just change the code of the new task.

Best regards

Mike T.

Member for

9 years 6 months

Thanks Mike, the only problem I have with that method is if I copy a task and it copies the code to the new task even though it's not allocated to the hammock of the original task. I wasn't sure if there was any other way of showing that the new task is not allocated to a hammock without doing it manually.

Member for

19 years 10 months

Hi Richard

Assign a code to each task and then assign the same code to the hammock.

Best regards

Mike T.