Importing XML file into Asta

Member for

19 years 10 months

Hi Amir

I never seem to have any problem importing Microsoft xml files into Asta - it is probably something in the source file that is causing the split.

You can try lining up the split tasks and use the Split/Join function to join them into a single task.

Best regards

Mike T.