Hi Robert

Haven't heard from you for some time - good to see someone else helping out on the Asta queries.

One small point - you have to rescedule the project to get the results.

Best regards

Mike Testro

Member for

19 years

Gary,

Yes, you can.

Right click on the title area of the table, hover over Add Column on the menu which appears, and then hover over Float to open a further menu - in this menu you will find Early Start, Early Finish, Late Start and Late Finish. Select one and it will appear in the table area, repeat for the remaining headings.