Is there a shortcut way of entering progress on ASTA?

Member for

10 years 2 months

Hi Mike

Thank you for that

Just tried it

You have to use "paste values" instead of "paste" option

Works a treat thanks!

Member for

19 years 10 months

Hi Yasine - welcome to planning planet.

Yes my method is very quick

Set your progress percentages into a spreadsheet against each task.

Make sure that the tasks on the Asta view are lined up with the spreadsheet - I do this by filtering the tasks with no restraints so only the tasks show.

It is essential that they DO line up.

Set up the chart progress column to show percent complete - save this as a view called progress entry.

Make sure your progess period is set to the correct data date.

Now copy / paste all the spreadsheet percent numbers into the progress column and reschedule - job done in 3 minutes max - even with 10,000 tasks.

Give it a try.

Best regards

Mike Testro