When copying tasks to another project you will have to copy the codes as well.
In version 10 & 11 when you copy tasks from one programme to another you are given the option to copy codes - resources and calendars as well.
If you missed it then I would suggest that make the copy again and pick up the other object that you want to copy.
Alternativel you can go into the first library and copy the codes and paste it into the new project - but then you will have to allocate them onto the copied tasks yourself.
I had a website called Planning Academy where you could download tutorials for use of Asta PowerProject - this was abandone about 3 years ago.
My current website is www.expertdelayanalysis.com but the only download is my Ebook - Principles of delay analysis.
In future of you want my direct advce it is best to send me a private message.
Member for
13 years 8 monthsThanks Mike
Thanks Mike
Member for
19 years 10 monthsHi Munaf - welcome to
Hi Munaf - welcome to Planning Planet
When copying tasks to another project you will have to copy the codes as well.
In version 10 & 11 when you copy tasks from one programme to another you are given the option to copy codes - resources and calendars as well.
If you missed it then I would suggest that make the copy again and pick up the other object that you want to copy.
Alternativel you can go into the first library and copy the codes and paste it into the new project - but then you will have to allocate them onto the copied tasks yourself.
I had a website called Planning Academy where you could download tutorials for use of Asta PowerProject - this was abandone about 3 years ago.
My current website is www.expertdelayanalysis.com but the only download is my Ebook - Principles of delay analysis.
In future of you want my direct advce it is best to send me a private message.
Best regards
Mike Testro