Asta Powerproject Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2015-02-09 11:35 Permalink Hi MikeThis is in two Hi Mike This is in two stages. First go to Tools > Default > Link and untick the draw curved box. Second select a link and then Ctrl A to highlight every link Right click any link and choose Properties and untick draw curved. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2015-02-09 11:35 Permalink Hi MikeThis is in two Hi Mike This is in two stages. First go to Tools > Default > Link and untick the draw curved box. Second select a link and then Ctrl A to highlight every link Right click any link and choose Properties and untick draw curved. Best regards Mike Testro
Member for
19 years 10 monthsHi MikeThis is in two
Hi Mike
This is in two stages.
First go to Tools > Default > Link and untick the draw curved box.
Second select a link and then Ctrl A to highlight every link
Right click any link and choose Properties and untick draw curved.
Best regards
Mike Testro