Also check you have the full licensed version of the software, not the limited free trial version. The trial version will open an XML file of any size but will enter read-only mode if there are more than 20 tasks...
I was just wondering if it is possible for example to change the heararchy of tasks, drag and drop, if the schedule was uploaded in to Asta Powerproject as XML version.
I just tryed to do all You suggested, but it is like schedule is frozen.
Sorry, if all of this is hard to understand and thank You again.
Member for
13 years 9 monthsAlso check you have the full
Also check you have the full licensed version of the software, not the limited free trial version. The trial version will open an XML file of any size but will enter read-only mode if there are more than 20 tasks...
Cheers,
Ben @ Asta
Member for
19 years 10 monthsHi KarinaIf you have opened
Hi Karina
If you have opened an XML file into Asta you will need to save it as a .PP file for it to work correctly.
Also check Help > User Level > Advanced to get access to all functions.
Best regards
Mike Testro
Member for
11 yearsHello MikeThank You for Your
Hello Mike
Thank You for Your reply.
I was just wondering if it is possible for example to change the heararchy of tasks, drag and drop, if the schedule was uploaded in to Asta Powerproject as XML version.
I just tryed to do all You suggested, but it is like schedule is frozen.
Sorry, if all of this is hard to understand and thank You again.
Karina
Member for
19 years 10 monthsHi Karena - welcome to
Hi Karena - welcome to planning planet.
I do not understand your question - in Asta Power Project a task is a task at the lowest level of the project hierarchy.
There is no such thing as a sub task.
A task can be put under a summary bar and summary bars can be summarised to create a hierarchy level of detail.
You can change a task into a milestone in a number of ways:
Right click on the task and Change Into milestone
Click and hold on the end of the task and drag it to zero duration
Type "0" in the duration box
The reverse changes a milestone into a task.
BTW there is no need to place your query in more than one topic or under a different name.
Best regards
Mike Testro - PP Moderator