Hi Chris,

Create a code for your key deliverable and apply it to the task with the constraint flag on it then insert a column that sources/filters for that code to display the RAG column.

Kind regards,

Craig

Member for

19 years 10 months

Hi Chris

Asta do not make it easy to apply formulas to the spreadsheet.

They should at least have a library of common formulae.

Perhaps this will come up in version 13.

Best regards

Mike Testro