The whole point about task per line mode is that you should not be able to start any section before the previous is 100% complete.
However the software can cope with out of sequence logic as the incomplete tasks will pile up past the data date leaving gaps in the completed sequence.
If you have FS logic between the In Line tasks then the sequence will be maintained or you can add FS logic to the uncomplete task in drop down mode.
Thanks for the responce. Yes correct, its in task per line mode and my senior wants it to remain like that so I am unable to drop the individual tasks down as it would complicate a fairly easy to read programme (its a finishes programme based on floors of appartments). I use code librarys for each task in the task per line mode so if all the tasks are not 100% complete the progress like stops at % complete i.e I may have 5 1w tasks, the first 2 are 100% the third is 40& and the 4th is 100% complete however the progress stays at the 40% date. Can I bring this forward or illustrate this task is still incomplete in another way without adding to the programmes content?
To enter progress on each task in the line you can either:
1. Click on the little + sign on the extreme left column and the tasks will drop down for progress.
2. Highlight to task line and "unroll" the tasks and the tasks become sigle items. You can then copy paste the progress and then "roll up" afterwards.
You can also show the tasks per line as a "line of balance" chart which is similar to a time / chain diagramme - fantastic for linear repetitive programmes.
Member for
19 years 10 monthsHi MarkThe whole point about
Hi Mark
The whole point about task per line mode is that you should not be able to start any section before the previous is 100% complete.
However the software can cope with out of sequence logic as the incomplete tasks will pile up past the data date leaving gaps in the completed sequence.
If you have FS logic between the In Line tasks then the sequence will be maintained or you can add FS logic to the uncomplete task in drop down mode.
Best regards
Mike Testro
Member for
13 years 6 monthsHi Mike, Thanks for the
Hi Mike,
Thanks for the responce. Yes correct, its in task per line mode and my senior wants it to remain like that so I am unable to drop the individual tasks down as it would complicate a fairly easy to read programme (its a finishes programme based on floors of appartments). I use code librarys for each task in the task per line mode so if all the tasks are not 100% complete the progress like stops at % complete i.e I may have 5 1w tasks, the first 2 are 100% the third is 40& and the 4th is 100% complete however the progress stays at the 40% date. Can I bring this forward or illustrate this task is still incomplete in another way without adding to the programmes content?
Member for
19 years 10 monthsHi MarkThe programme is in
Hi Mark
The programme is in "Task per Line" mode.
To enter progress on each task in the line you can either:
1. Click on the little + sign on the extreme left column and the tasks will drop down for progress.
2. Highlight to task line and "unroll" the tasks and the tasks become sigle items. You can then copy paste the progress and then "roll up" afterwards.
You can also show the tasks per line as a "line of balance" chart which is similar to a time / chain diagramme - fantastic for linear repetitive programmes.
Best regards
Mike Testro