Asta Powerproject Member for 12 years 8 months Member for 12 years 9 months Submitted by chris77 on Thu, 2013-10-10 13:35 Permalink Thats great Mike.Thanks Thats great Mike. Thanks Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-10-10 12:29 Permalink Hi ChrisUsing File > Save As Hi Chris Using File > Save As > you can go down to v 11. From there you may be able to go down further. Best regards Mike Testro Member for 12 years 8 months Member for 12 years 9 months Submitted by chris77 on Thu, 2013-10-10 09:21 Permalink Mike,Many thanks for that.How Mike, Many thanks for that. How can I convert version 12 file into old version 10 ? any idea? please reply. Cheers Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-10-10 07:31 Permalink Hi ChrisPowerproject has a Hi Chris Powerproject has a very simple filter system. For critical activities you just select Float & Criticality in the filter drop down and then tick critical tasks - the default is zero float. You then select the chart to show the critical activity. Best regards Mike Testro Member for 12 years 8 months Member for 12 years 9 months Submitted by chris77 on Wed, 2013-10-09 23:55 Permalink Ben, Mike and others can help Ben, Mike and others can help me please on above issues? thanks Log in or register to post comments
Member for 12 years 8 months Member for 12 years 9 months Submitted by chris77 on Thu, 2013-10-10 13:35 Permalink Thats great Mike.Thanks Thats great Mike. Thanks
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-10-10 12:29 Permalink Hi ChrisUsing File > Save As Hi Chris Using File > Save As > you can go down to v 11. From there you may be able to go down further. Best regards Mike Testro
Member for 12 years 8 months Member for 12 years 9 months Submitted by chris77 on Thu, 2013-10-10 09:21 Permalink Mike,Many thanks for that.How Mike, Many thanks for that. How can I convert version 12 file into old version 10 ? any idea? please reply. Cheers
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2013-10-10 07:31 Permalink Hi ChrisPowerproject has a Hi Chris Powerproject has a very simple filter system. For critical activities you just select Float & Criticality in the filter drop down and then tick critical tasks - the default is zero float. You then select the chart to show the critical activity. Best regards Mike Testro
Member for 12 years 8 months Member for 12 years 9 months Submitted by chris77 on Wed, 2013-10-09 23:55 Permalink Ben, Mike and others can help Ben, Mike and others can help me please on above issues? thanks
Member for
12 years 8 monthsThats great Mike.Thanks
Thats great Mike.
Thanks
Member for
19 years 10 monthsHi ChrisUsing File > Save As
Hi Chris
Using File > Save As > you can go down to v 11.
From there you may be able to go down further.
Best regards
Mike Testro
Member for
12 years 8 monthsMike,Many thanks for that.How
Mike,
Many thanks for that.
How can I convert version 12 file into old version 10 ? any idea?
please reply.
Cheers
Member for
19 years 10 monthsHi ChrisPowerproject has a
Hi Chris
Powerproject has a very simple filter system.
For critical activities you just select Float & Criticality in the filter drop down and then tick critical tasks - the default is zero float.
You then select the chart to show the critical activity.
Best regards
Mike Testro
Member for
12 years 8 monthsBen, Mike and others can help
Ben, Mike and others can help me please on above issues?
thanks