It depends how you have set up your resource modelling.
If you have many different resources representing each trade then you will need two columns for each one.
In Table Definition select Resource and then Effort
You now have to select your resource and set the data to either Live or whatever Baseline you are using.
You will now get live data in the columns.
You have to change the setting for each resource which is cumbersome - which is why I use only one resource called Hours - which is common for all tasks for modelling purposes.
I then use a code for each trade resource for filtering and histograms.
Member for
19 years 10 monthsHi Ronan It depends how you
Hi Ronan
It depends how you have set up your resource modelling.
If you have many different resources representing each trade then you will need two columns for each one.
In Table Definition select Resource and then Effort
You now have to select your resource and set the data to either Live or whatever Baseline you are using.
You will now get live data in the columns.
You have to change the setting for each resource which is cumbersome - which is why I use only one resource called Hours - which is common for all tasks for modelling purposes.
I then use a code for each trade resource for filtering and histograms.
Best regards
Mike Testro