Import of .xer created in Asta into P6 v6.2: known problems?

Member for

24 years 6 months

Importing form one product to another will usually give a different answer unless the schedules are very simple as they all have different algorithums.

It is my experiance that Asta does this far better than any of the other products but manual intervention is usually required when going from one product to another.

 

Paul E Harris