I'm not entirely sure that your post isn't an advert for application development services... However, it does give me an excuse to update this thread on the development I mentioned earlier in the year!
Site Progress Mobile, a mobile application on Android & iOS to work in conjunction with Asta Powerproject, is coming in the New Year. Hopefully Santa will be delivering a beta version to interested parties shortly after dropping off the rest of his Christmas presents. A full launch will then follow including demonstrations at our National User Forum in London, 26th March 2014.
It is looking like an ideal tool for connecting the reality of the build with the office-based planners!
Developing ASTA for ipad by using ipad application development is not an easy thing, I really appreciate this effeort made. No doubt ASta App is great option for us who regulary use mobile devices.
Funnily enough, we have exactly such an app in development as we speak - perhaps you've seen a copy of our product roadmap?!?
The focus of our support for mobile devices will be around the easy reporting of activity progress from remote locations; in other words, the perfect tool to allow site managers to report actual progress against scheduled activity. This will function regardless of network connectivity, so you don't have to rely on having Wi-fi/3G/4G on a building site! It is also equally applicable to our customer base outside of construction who want to record progress information but without needing to use our existing timesheet system.
Do keep an eye on our website or sign up for our 'Powerlines' newsletters in order to receive updates on our release schedule for these new modules.
I am thinking I will use my Smart Board to project the game with big screen and sounds. This will certainly get my students engaged by bringing them up to the board, selecting the plays, and getting ipad application development help for answers from the audience. Looking forward to Friday already.
Member for
18 years 5 months
Member for18 years5 months
Submitted by Tekin Guvercin on Mon, 2012-07-16 15:36
ASTA has mobile application. Enterprise version also has free of Charge IPAD & IPhone reporting. This is simple and very effective module for Management. Please see presentation how it work from as following link.
Member for
13 years 9 monthsHi Patii, I'm not entirely
Hi Patii,
I'm not entirely sure that your post isn't an advert for application development services... However, it does give me an excuse to update this thread on the development I mentioned earlier in the year!
Site Progress Mobile, a mobile application on Android & iOS to work in conjunction with Asta Powerproject, is coming in the New Year. Hopefully Santa will be delivering a beta version to interested parties shortly after dropping off the rest of his Christmas presents. A full launch will then follow including demonstrations at our National User Forum in London, 26th March 2014.
It is looking like an ideal tool for connecting the reality of the build with the office-based planners!
Ben
Member for
11 years 10 monthsHi,Developing ASTA for ipad
Hi,
Developing ASTA for ipad by using ipad application development is not an easy thing, I really appreciate this effeort made. No doubt ASta App is great option for us who regulary use mobile devices.
Member for
13 years 9 monthsHi Claudia,Funnily enough, we
Hi Claudia,
Funnily enough, we have exactly such an app in development as we speak - perhaps you've seen a copy of our product roadmap?!?
The focus of our support for mobile devices will be around the easy reporting of activity progress from remote locations; in other words, the perfect tool to allow site managers to report actual progress against scheduled activity. This will function regardless of network connectivity, so you don't have to rely on having Wi-fi/3G/4G on a building site! It is also equally applicable to our customer base outside of construction who want to record progress information but without needing to use our existing timesheet system.
Do keep an eye on our website or sign up for our 'Powerlines' newsletters in order to receive updates on our release schedule for these new modules.
Best wishes,
Ben @ Asta
Member for
12 years 3 monthsI guess this is something
I guess this is something that they should work on to. Having an ASTA app for most popular devices can be a best options for many users and members.
Regards,
Claudia Owen
Member for
12 years 5 monthsI am thinking I will use my
I am thinking I will use my Smart Board to project the game with big screen and sounds. This will certainly get my students engaged by bringing them up to the board, selecting the plays, and getting ipad application development help for answers from the audience. Looking forward to Friday already.
Member for
18 years 5 monthsDear Derya,ASTA has mobile
Dear Derya,
ASTA has mobile application. Enterprise version also has free of Charge IPAD & IPhone reporting. This is simple and very effective module for Management. Please see presentation how it work from as following link.
http://www.youtube.com/watch?v=DucPxlhlCU0&feature=youtu.be&a
Report Template also modify and custumize for each project.
Please let me know if you need any more explanation,
you can get trial from www.astadev.com
Regards
Tekin