Does anyone (successfully) record as-built data against a baseline in Asta ??

Member for

22 years 4 months

Many thanks everyone.

Yes, I contacted asta support and they recommend using "Overall Percentage Complete". Now this SEEMS to do the job, however I have used it before and encountered the problems with Asta moving previously "As Built" start dates. I will eport back if / when this happens.

 

 

Member for

21 years 8 months

Tom,

I had the same issue with Spider Project as it displays values as well as bars on a single activity line with height increased as to accommodate up to 4 bars (Current Early and Late at center vertical alignment, Baseline Early shifted upwards, Compared Early shifted downward) and compared values on different columns, not on different lines.

I figured it out by creating a Portfolio of versions to be compared. I believe the details on how job versions are saved and transferred might differ, also we have the option to create multiple WBS but for your need only one is enough.

Look at the following figure and perhaps you can figure it out, I will not be of much help as Spider interface differ but maybe others will.

Photobucket

Best regards,

Rafael

Member for

14 years 9 months

Hi Tom

If you send a copy of your ASTA project to ASTA technical support,

They can look look at it and advise what you have missed.

 

I have been using ASTA for a very long time and the support team are super.

You can spend many hours looking at a problem which they can solve in minutes

 

I have contacted them a number of times about very major problem, but when they looked at the programme, it is a very simple problem and its something I have done.

They also use netview, which I think is a great piece of software 

 

100% marks to ASTA technical support Lads and Lasses

Member for

24 years 4 months

Tom,

Have you tried discussing this problem with ASTA technical support?

Member for

14 years 9 months

Hi Mike / Tom

Looked the this web site - Very poor site, Got bored, will not be going back there or recommend it.

No interaction at all, Clicked on every page no responce

just add to cart at a cost

Clicked on try before you buy and got

Error 404 - Not Found 

Member for

22 years 4 months

Many thanks Mike, will check the website out

 

Tom

Member for

22 years 4 months

Many thanks Mike, will check the website out

 

Tom

Member for

19 years 10 months

Hi Tom

This is the way I do it for a Time Impact analysis and it is vital that you DO NOT SAVE THE FILE.

1.  Open your contract programme

2.  Delate all the logic - select any link then Edit Select All and delete - also remove all constraints by filtering.

3.  Copy paste your As Built start and finish dates from your spreadsheet

4.  Creat a Baseline using the Baseline What if Manager

5.  Close the file BUT DO NOT SAVE IT.

6.  Open the file and open the created baseline.

It is a different method if you are doing an As Built but For analysis

All of this and much much more is in the Tuition Modules at Planning Academy.

www.planningacademy.org

Best regards

Best regards

Mike Testro