Asta Powerproject Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2011-05-24 05:37 Permalink Hi Lee Read what Chris told Hi Lee Read what Chris told you and set the start date to zero at week 1. It also helps if you set the same start date in File > properties. Best regards Mike T. Member for 20 years 6 months Member for 20 years 6 months Submitted by Lee Mallek on Mon, 2011-05-23 16:57 Permalink Many thanks for your Many thanks for your replys. It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2? Has anyone encountered this? Member for 15 years 4 months Member for 15 years 5 months Submitted by Chris Rymer on Fri, 2011-05-20 14:17 Permalink Lee Mike is correct about the Lee Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from. Chris Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2011-05-18 05:20 Permalink Hi Lee Right click the date Hi Lee Right click the date zone - click Insert Line - select Elapsed Units Move the line up or down to the required postion. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2011-05-24 05:37 Permalink Hi Lee Read what Chris told Hi Lee Read what Chris told you and set the start date to zero at week 1. It also helps if you set the same start date in File > properties. Best regards Mike T.
Member for 20 years 6 months Member for 20 years 6 months Submitted by Lee Mallek on Mon, 2011-05-23 16:57 Permalink Many thanks for your Many thanks for your replys. It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2? Has anyone encountered this?
Member for 15 years 4 months Member for 15 years 5 months Submitted by Chris Rymer on Fri, 2011-05-20 14:17 Permalink Lee Mike is correct about the Lee Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from. Chris
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Wed, 2011-05-18 05:20 Permalink Hi Lee Right click the date Hi Lee Right click the date zone - click Insert Line - select Elapsed Units Move the line up or down to the required postion. Best regards Mike Testro
Member for
19 years 10 monthsHi Lee Read what Chris told
Hi Lee
Read what Chris told you and set the start date to zero at week 1.
It also helps if you set the same start date in File > properties.
Best regards
Mike T.
Member for
20 years 6 monthsMany thanks for your
Many thanks for your replys.
It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2?
Has anyone encountered this?
Member for
15 years 4 monthsLee Mike is correct about the
Lee
Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from.
Chris
Member for
19 years 10 monthsHi Lee Right click the date
Hi Lee
Right click the date zone - click Insert Line - select Elapsed Units
Move the line up or down to the required postion.
Best regards
Mike Testro