Gaps in Critical Path

Member for

19 years 10 months

Hi Craig

There will always be problems when different calendars clash on a single task with multiple resources.

Do you have a single task for "pour concrete"?

That would be a way to solve your problem - set the 5 day calendar on the Pour Concrete task and on the resource modelling dialogue tick the "use task calendar" button.

Best regards

Mike Testro