Its "Hide pregressed sections when filter applied" its in the filter properties.
I found the solution. The issue was Id selected hide progressed tasks when I created a filter. This apparently then ticked the "Uncompleted" box in the Progress section of the format bar.
When I switched off the filter I expected to see my completed work again, not the case.
You have to untick "Uncompleted", it doesnt untick itself.
Member for
19 yearsRE: Hide Progressed Tasks
Hello Mike,
Its "Hide pregressed sections when filter applied" its in the filter properties.
I found the solution. The issue was Id selected hide progressed tasks when I created a filter. This apparently then ticked the "Uncompleted" box in the Progress section of the format bar.
When I switched off the filter I expected to see my completed work again, not the case.
You have to untick "Uncompleted", it doesnt untick itself.
Kind regards,
Craig Adams
Member for
19 years 10 monthsRE: Hide Progressed Tasks
Hi Craig
I assume you are using the toggle buttons in:
Format > Barchart > Progress > Drawing
With three Options
All Completed Uncompleted
You mention "hide if task progressed" I have not been able to find this particular function - even in the "hide marked items" format.
Let me know where you found it.
Best regards
Mike Testro