Baselines and learning more about how Asta Works

Member for

15 years 10 months

Hi Mike,



11.02 has this new feature which I think goes some way to resolving your wish I think. You can get 11.02 for the support section of astadev.com.



Save baselines using a relative path to maintain the link between project and baseline when they are copied to a different folder

When you create a baseline, a link is established between the baseline and the project from which it was baselined so that the baseline can be located when you open it from within the project. During the baseline creation process, you can now choose to save baselines into the same folder as the project by entering a filename for the baseline and not specifying a path. If you do this, you can copy the project and its baselines to another folder subsequently without the link between them being lost.



Regards



Andrew

Member for

19 years 10 months

Hi Andrew



On my wish list is the facility to embed baselines - just like borders in v 10.



I always save baselines in the same file as the main programme.



Best regards



Mike Testro

Member for

15 years 10 months

Hi Craig,



When you go to enterprise all the baselines are saved in the once database so there will be no prblems there.



In the standalone version you are correct a separate file is created. If you copy the project somwhere else you need to copy the baseline as well. When you have copied it, you can go into format bar chart, reference the baseline and you can find it.



Andrew