Interesting reading, think Im going to be one of those mere mortals that feed you work.
My tender schedules arent that detailed, they are extra work I do for builders in my spare time and they use them in their tender submissions. The detailed schedules Im doing now are for land development projects that go through to construction. These are doing my head in, Ive done them in MSP but theyre starting to fall over and the file/s are crashing often. Am learning PP and very impressed, am keen to apply your methodology but need to learn to use the codes etc. Love the ability to have the file structure on the left and open up different sections for easy linking.
Member for
19 yearsRE: Hours default in annotation?
Hi Mike,
Interesting reading, think Im going to be one of those mere mortals that feed you work.
My tender schedules arent that detailed, they are extra work I do for builders in my spare time and they use them in their tender submissions. The detailed schedules Im doing now are for land development projects that go through to construction. These are doing my head in, Ive done them in MSP but theyre starting to fall over and the file/s are crashing often. Am learning PP and very impressed, am keen to apply your methodology but need to learn to use the codes etc. Love the ability to have the file structure on the left and open up different sections for easy linking.
Cheers,
Craig
Member for
19 years 10 monthsRE: Hours default in annotation?
Hi Craig
Because it is sloppy planning and counter productive when problems occur.
Use only FS links and you will get a better critical path status.
There are many threads on this topic - do a search on Bottom Up Planning.
Best regards
Mike Testro
Member for
19 yearsRE: Hours default in annotation?
Hello Mike,
Found what I was looking for, simply change the default time unit in the tool bar at the top. Man I spent hours looking for this!
Why wouldnt you use a lead lag in a case where you know tasks can start before the preceding task is completed?
Kind regards,
Craig
Member for
19 years 10 monthsRE: Hours default in annotation?
Hi Craig
First check your default time unit and set it to days.
When you type the number in the lead lag box use the corect suffix - 1d - 24h - 1w etc.
This will give you working day lags - use 1ed - 24eh etc to give an elapsed duration or calendar time.
The only legitimate use of lead lags is FS +ed to represent concrete curing or drying out screeds etc - no other use is valid.
You can also set lags to % of work - but why bother.
Best regards
Mike Testro