Hi Mike

Thanks for your prompt response. Its really good tip.

Member for

19 years 10 months

Hi Bill



In version 10 select the bar and right click on the task for the task drop down.



Left click on the "Mark for Hiding" option.



Repeat for all other tasks.



In the Format drop down click Hide Marked Items.



The marked tasks disapear.



Best regards



Mike Testro