As Paul wrote you do need to set the programme time units to minutes to get the results that you require - there is usually a drop down menu on the "Standard" icon menu.
Also make sure that the work pattern in your callendar does not have any Non-Work periods in the time zone that you are looking at.
Finally make sure that any resources attached to the task have the same calendar - this can be done in the modelling dialogue by ticking the "Calendar as Task" box.
There will be a full description of how to apply these items in the Help directory.
Member for
19 years 10 monthsRE: Help on drawing bars
Hi Christina
As Paul wrote you do need to set the programme time units to minutes to get the results that you require - there is usually a drop down menu on the "Standard" icon menu.
Also make sure that the work pattern in your callendar does not have any Non-Work periods in the time zone that you are looking at.
Finally make sure that any resources attached to the task have the same calendar - this can be done in the modelling dialogue by ticking the "Calendar as Task" box.
There will be a full description of how to apply these items in the Help directory.
Best regards
Mike Testro
Member for
24 years 6 monthsRE: Help on drawing bars
You need to change your snap Options. Do a search in help for snap and it will tell you all about it.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.primavera.com.au