1st time using Asta PowerProject -Any tips?

Member for

11 years 2 months

Thank you Paul this is just what I am looking for. 

Member for

19 years 10 months

Hi Gary



The one thing that drives new PP users nuts - especialy those migtrating from P3 P6 is the "Views" menu.



This allows you to set up different forms of presentation and give it a label - for instance only summary bars - or a particular trade filter and then freeze it as a view.



This is a very useful tool when you know how to use it but if you don’t know what you are doing you could find yourself inadvertantly "flipping" between someone elses pre-determined veiws and you won’t know what is happening.



Spend your 1st 10 minutes in the help section on Views and take a bit of time practising switching so you know what is happening when you find yourself staring at a completely different screen.



Otherwise send me a PP message and I will give you my phone number so I can assist directly.



Best regards



Mike Testro

Member for

24 years 6 months

There is an article on my web sites that you may find useful under Technical Papers titled "Asta Power Project - an introduction".



This document is designed to assist people who are using SureTrak, P3, Primavera Enterprise or Microsoft Project to learn the basics of PowerProject to create and progress an unresourced schedule.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au