Converting ASTA power Project File to P3

Member for

22 years 5 months

Nokhez - if you want some local support, feel free to contact us at Solid Support 02 9743 4666.



We run a helpdesk for Asta Power Project users who have maintenance agrrements with us.



help@solidsupport.com.au



Good to see your company (TBH) are trialing / experimenting with the software.

Member for

19 years 10 months

Hi Nokhez.



I am assuming that you have PowerProject v 10 and P3 on the same computer and you are using the standard Icons in PowerProject.



The error note indicates that you are using an invalid calendar or workpattern that is not used on P3.



I suggest you review your calendars and apply a standard 8 hr day 5 day week on PowerProject tasks before trying to convert.



Best regards



Mike Testro